Central agencies engaged in the road construction work under the PM Gramin Sadak Yojana (PMGSY) have often faced criticism for their shoddy performance resulting in tardy and poor quality work. The state government has now asked them to hand over those roads which could not be completed for want of contractors.
Minister of rural works department Brishen Patel acknowledged the fact that a large number roads under PMGSY could not be completed ostensibly because contractors were not coming forward to file tenders.
The minister, who was replying to a short notice question of Ram Dev Verma (CPM), informed the Vidhan Sabha on Wednesday about the problems faced by central agencies in road construction.
"As per central government guidelines , there is no provision for revision in estimate and price adjustment in the road construction work. This is why contractors were not willing to file tenders floated by the central agencies. But we have now asked them to hand over the work to us," the minister said, adding the state government had a provision of Rs 653 crore from its kitty to meet additional cost.
The minister admitted that central agencies had accepted the proposal to hand over the work to state agencies which will be inviting tenders for ensuring speedy completion of work."Since the government was willing to revise the cost estimate, the state agencies will not face any problem in engaging the contractors," the minister said.
The minister informed the House that about 30000 km road was to be constructed under PMGSY and both central and state agencies were involved in construction work. "But construction work of the central agencies were of poor quality. More importantly, the work was executed in a tardy manner. So we requested the Centre to allow us to complete the work by our own agencies," the minister said. link